| Description: | CID/HBLL Service Agreement for 2005 | ||
| Projects: | CID | ||
| Priority: | 50 | Task ID: | 875 |
| Long Description: | |||
| Status: | Open | ||
| Owner: | Lund, Bill | Contributors: | Monsen, David |
| Due: | TBD | Opened: | 1/25/2005 |
| Changed: | 2/3/2005 | ||
| 1/24/2005 | Discussed this at the CID managers' meeting today. Jon Mott asked that I work with David Monsen. I need to:
| ||
| 2/3/2005 | Sent the draft to Brett and Ryan to review. | ||
| Description: | HBLL Add Wireless to HBLL; Current Infrastructure: Wireless Network Installations | ||
| Projects: | CID, Creative Works, HBLL, LIS, OIT, OIT Projects | ||
| Priority: | 99 | Task ID: | 317 |
| Long Description: | Implement wireless in the library. | ||
| Status: | Open | ||
| Owner: | Hill, Brett | Contributors: | Elison, Nyle Lund, Bill |
| Due: | TBD | Opened: | 11/13/2002 |
| Changed: | 3/9/2005 | ||
| 1/25/2005 | Betty Walling writes: Taylor Snyder, who was managing the wireless projects, has been off sick for quite sometime. He is back today. He reports that the engineering is done but Bart is waiting for antennas. Taylor will update Project Office as soon as he can. He has a lot of catching up to do so give him a couple days to get the updates into Project Office.I've asked whether there is any way to track this progress. | ||
| 2/3/2005 | There is an OIT project, documented in the title of the task. I want a map showing the locations of all of the wireless access points in the ceilings so that we can support the system. I turned in an AHD request #644806. Emailed Nyle asking how we track progress. | ||
| 3/1/2005 | We received a map, but it didn't show where the wireless hubs were located. Also, it only included the first four floors. I reopened the ticket in AHD. | ||
| 3/3/2005 | OIT is wiring the conference rooms, specifically: 1120, 1131, 2070, 2103, 2104, 2238, 2824, 3420 and 6525. | ||
| 3/9/2005 | As of today there was no wireless in room 1131. Emailed the project manager, Taylor Synder with this information. | ||
| Description: | Install Wireless in CID | ||
| Projects: | CID | ||
| Priority: | 99 | Task ID: | 661 |
| Long Description: | CID has requested that wireless be installed in their entire new area. | ||
| Status: | Open | ||
| Owner: | Lund, Bill | Contributors: | |
| Due: | TBD | Opened: | 1/23/2004 |
| Changed: | 1/25/2005 | ||
| 1/23/2004 | David Monsen sent a request to Betty Walling today. OIT is engineering wireless in the building in the near future, so CID should be included. | ||
| 1/25/2005 | It appears that this was never requested. | ||