Lee Library Information Systems Task List
CID

Description: CID/HBLL Service Agreement for 2005
Projects: CID
Priority: 50 Task ID: 875
Long Description:
Status: Open
Owner: Lund, Bill Contributors: Monsen, David
Due: TBD Opened: 1/25/2005
Changed: 2/3/2005  
1/24/2005 Discussed this at the CID managers' meeting today. Jon Mott asked that I work with David Monsen. I need to:
  • Find last year's agreement
  • Update it with support for servers
  • Review funding model
  • Review with Brett
  • Review with Nabil
  • Review with Randy and Julene
  • Take to David Monsen
  • Take to Jon Mott.
2/3/2005 Sent the draft to Brett and Ryan to review.
Description: HBLL Add Wireless to HBLL; Current Infrastructure: Wireless Network Installations
Projects: CID, Creative Works, HBLL, LIS, OIT, OIT Projects
Priority: 99 Task ID: 317
Long Description: Implement wireless in the library.
Status: Open
Owner: Hill, Brett Contributors: Elison, Nyle
Lund, Bill
Due: TBD Opened: 11/13/2002
Changed: 3/9/2005  
1/25/2005 Betty Walling writes:
Taylor Snyder, who was managing the wireless projects, has been off sick for quite sometime.  He is back today.  He reports that the engineering is done but Bart is waiting for antennas.  Taylor will update Project Office as soon as he can.  He has a lot of catching up to do so give him a couple days to get the updates into Project Office.
I've asked whether there is any way to track this progress.
2/3/2005 There is an OIT project, documented in the title of the task.

I want a map showing the locations of all of the wireless access points in the ceilings so that we can support the system. I turned in an AHD request #644806.

Emailed Nyle asking how we track progress.

3/1/2005 We received a map, but it didn't show where the wireless hubs were located. Also, it only included the first four floors. I reopened the ticket in AHD.
3/3/2005 OIT is wiring the conference rooms, specifically: 1120, 1131, 2070, 2103, 2104, 2238, 2824, 3420 and 6525.
3/9/2005 As of today there was no wireless in room 1131. Emailed the project manager, Taylor Synder with this information.
Description: Install Wireless in CID
Projects: CID
Priority: 99 Task ID: 661
Long Description: CID has requested that wireless be installed in their entire new area.
Status: Open
Owner: Lund, Bill Contributors:
Due: TBD Opened: 1/23/2004
Changed: 1/25/2005  
1/23/2004 David Monsen sent a request to Betty Walling today. OIT is engineering wireless in the building in the near future, so CID should be included.
1/25/2005 It appears that this was never requested.